Need the best report inside C_TSCM42_66 analyze qualification? Next you should acquire test human brain places to your support and also an incredible efficiency. Effortlessly plan C_TSCM42_66 exam pdf demo in just months, with all the aid coming from test VCE and also trial inquiries accessible together with merely a basic simply click on your desktop display screen. Our own newest C_TSCM42_66 training and also original advice components which is offered by means of test VCE will be the finest options for transferring the particular test qualification inside the initial move.
QUESTION 1
In which master data object do you set the standard values for an operation?
A. Material Master
B. Work Center
C. Routing
D. Production Resource/Tool (PRT)
Answer: C
QUESTION 2
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
A. Approved master recipes
B. Digital signature
C. Electronic batch record
D. Availability check
E. Resource selection
Answer: ABC
QUESTION 3
In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot). What could be the reason?
A. There are no planned orders or production orders present.
B. The repetitive manufacturing indicator has been set.
C. There is no valid production version for this material.
D. There are no requirements present.
Answer: C
QUESTION 4
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
A. Rescheduling the operation
B. Posting the goods receipt for the production order
C. Confirming the operation
D. Setting the status technically complete (TECO)
E. Reducing the order quantity
Answer: CDE
QUESTION 5
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
A. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
B. Consumption takes place with the planning material.
C. Consumption can reduce the total originally planned production quantity.
D. Consumption can increase the total originally planned production quantity.
Answer: D
QUESTION 6
Which of the following elements can be used in a process order? (Choose three)
A. Process instructions
B. Parallel sequences
C. Relationships
D. Suboperations
E. Phases
Answer: ACE
QUESTION 7
You want to create a new material that – is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directly. Which standard SAP material type do you use?
A. NLAG (non-stock material)
B. FERT (finished product)
C. ROH (raw material)
D. HAWA (trading good)
Answer: C
http://www.passleader.com/c-tscm42-66.html
Basically downloads available the particular awesome C_TSCM42_66 components to gauge our own test preparing advice if you need to get ready by means of test inquiries regarding qualification. Excellent accomplishment is currently achievable inside test qualification by means of our own test training and also test human brain eliminate, preferred alternatives to find the best brings about qualification tests. C_TSCM42_66 sample questions and also audio tracks test will be the right type of substance to adopt aid coming from, so that you can understand exactly about reaching a top report inside qualification and also make certain the accomplishment and also awesome efficiency. C_TSCM42_66 trial and also test inquiries you will need to make suggestions from the means of preparing regarding test qualification although removing any chances regarding blunders and also disappointment.